Public Service Company takes another step to close units at San Juan Generating Station

From the Farmington Daily Times - The Public Service Company of New Mexico has taken another step to meet federal emissions rules at San Juan Power Generating Station and close two units at San Juan Generating Station.
     In December last year, PNM submitted a filing with the New Mexico Public Regulatory Commission to gain approval for processes that would enable the generating station to meet federal emission standards. The filing contains a proposal to close two units at the station by the end of 2017, to reroute power from Palo Verde Nuclear Generating Station to serve PNM customers and to install emission reducing technology, all of which need PRC approval to happen.
     According to the executive summary of the filing, PNM is proposing to close units two and three to comply with the Environmental Protection Agency's Regional Haze Rule. "Approval of PNM's Application will also enable the company to move forward with plans to reduce its use of coal and significantly increase its use of cleaner fuels, including natural gas and solar," the filing stated.
     As a result, PNM is asking for 134 megawatts of power from a unit in Palo Verde Nuclear Generating Station to be used to replace power lost as a result of the closures. PNM has partial ownership in one unit at the nuclear facility.
     PNM has future plans to build a 144 megawatt natural gas power facility to be used for peak usage, said PNM spokeswoman Valerie Smith, and also build a 40 megawatt solar facility. PNM will ask PRC to approve those plans in the future. More